Luxury Hotel, MA

Housed 161 hotel rooms, had their 10Hp booster system fail on Thursday morning. Towle Whitney was called at 10am, and was on the job at 2pm. All of the needed components were in-stock at the shop, which resulted in a 24 hour turn-around, with delivery of a 5Hp duplex booster system on Friday afternoon. The energy savings from the VFD controls and 5Hp pumps of the newly installed system will pay for itself in full in approximately three years.

case study

10 HP Constant Speed Pump

case study

5HP VFD Booster Pump System